Your Views and Next Steps

As we develop our proposals, we would like to understand what you think. The comments we receive through this consultation will inform our design process as we progress towards an application for planning permission. 

Our survey closed on 31st January 2024.

 

Please note that the comments on this consultation do not constitute formal representations on a planning application. Once an application is submitted there will be period where the public can make representations to Falkirk Council.

This is the first stage in a two stage pre-application consultation process, and after reviewing your feedback from this event we will undertake further consultation on the scheme early next year before our planning application is submitted.
 

Our current timeline is as follows:

Second consultation event

February / March 2024

Planning submission

April 2024

Period for formal representations on planning application

3 weeks following submission

Falkirk Council consideration of application

4 months

Grant of planning permission in principle

August 2024

Application for Matters Specified in Conditions for first phases

October 2024

Construction commences

January 2025