Falkirk Gateway
Public Consultation
Your Views and Next Steps
As we develop our proposals, we would like to understand what you think. The comments we receive through this consultation will inform our design process as we progress towards an application for planning permission.
Our survey closed on 31st January 2024.
Please note that the comments on this consultation do not constitute formal representations on a planning application. Once an application is submitted there will be period where the public can make representations to Falkirk Council.
This is the first stage in a two stage pre-application consultation process, and after reviewing your feedback from this event we will undertake further consultation on the scheme early next year before our planning application is submitted.
Our current timeline is as follows:
Second consultation event
February / March 2024
Planning submission
April 2024
Period for formal representations on planning application
3 weeks following submission
Falkirk Council consideration of application
4 months
Grant of planning permission in principle
August 2024
Application for Matters Specified in Conditions for first phases
October 2024
Construction commences
January 2025